Project Name: The Digital Hamlet Initiative – [Municipality Name]
Client: [Municipality Name or Local Cooperative Entity]
Vendor: DeReticular
SOW Version: 1.0
Date: October 30, 2025
1.0 Executive Summary
This Statement of Work (SOW) outlines the scope, deliverables, timeline, and costs associated with the deployment of a 1,000-node, distributed NVIDIA H100 AI supercomputer (the “AI Cluster”) within [Municipality Name]. This project is the foundational pillar of the Rural Infrastructure Operating System (RIOS), designed to create a sovereign, self-funding economic engine for the community.
The AI Cluster will not be a centralized data center but a distributed network of compute nodes hosted by local businesses, public facilities, and community members (“Hosts”). Connected via a resilient Wi-Fi 7 mesh network, this cluster will serve two primary functions:
- Provide world-class AI compute capacity to the global market, generating significant revenue for the community.
- Serve as the computational backbone for the local RIOS ecosystem, empowering local businesses in energy, transportation, agriculture, and entrepreneurship.
This SOW covers the end-to-end process from initial site planning and infrastructure deployment to software orchestration and commercial go-live.
2.0 Project Goals and Objectives
The primary objectives of this engagement are:
- Deploy Infrastructure: To successfully deploy and bring online 1,000 NVIDIA H100 server nodes across a geographically distributed area within [Municipality Name].
- Establish Connectivity: To build a robust, high-performance Wi-Fi 7 mesh network that provides the necessary connectivity for the cluster’s intended workloads.
- Implement Orchestration: To install and configure a sophisticated software layer for managing, scheduling, and monetizing the distributed compute resources.
- Achieve Commercial Viability: To launch a public-facing portal for the sale of AI compute time, processing the first commercial transaction.
- Enable the RIOS Ecosystem: To provide the foundational infrastructure required for local RIOS-affiliated entities to build upon.
3.0 Scope of Work
The project will be executed in five distinct phases:
Phase 1: Planning, Design & Host Recruitment (T+0 to T+3 Months)
- 3.1 Site & Network Survey: Conduct a detailed geographical and RF survey of [Municipality Name] to create an optimal Wi-Fi 7 mesh network design and identify potential node locations.
- 3.2 Architecture Design: Finalize the detailed technical architecture for the server nodes, power/cooling requirements, and the software orchestration stack.
- 3.3 Community Engagement & Host Recruitment: Launch a community outreach program to identify and sign agreements with 1,000 local Hosts. Develop incentive models (revenue share, free internet, etc.).
- 3.4 Procurement & Logistics: Procure all necessary hardware, including servers, networking gear, and deployment kits.
Phase 2: Physical Infrastructure Deployment (T+4 to T+9 Months)
- 3.5 Site Preparation: Work with Hosts to prepare their locations, ensuring adequate power, cooling, and physical security for each server node.
- 3.6 Wi-Fi 7 Mesh Deployment: Install and configure all Wi-Fi access points and backhaul connections as per the network design.
- 3.7 Server Node Installation: Systematically deploy and install the 1,000 NVIDIA H100 server nodes at the prepared Host locations.
- 3.8 Network Commissioning: Bring the mesh network online and conduct extensive testing to ensure stable connectivity and performance across all nodes.
Phase 3: Software Orchestration & Integration (T+8 to T+12 Months)
- 3.9 Cluster Orchestration Layer: Deploy a Kubernetes-based (or similar) orchestration platform across all 1,000 nodes to manage them as a single entity.
- 3.10 Workload & Resource Management: Install and configure a workload manager (e.g., Slurm, Kubeflow) to handle job scheduling, resource allocation, and user permissions.
- 3.11 RIOS Integration Layer: Deploy the core RIOS software, providing APIs and data pipelines to be used by local friendly organizations (Agra Dot Energy, Kurb Kars, etc.).
- 3.12 Monitoring & Management Stack: Implement comprehensive monitoring tools (e.g., Prometheus, Grafana, DCGM) to track the health, performance, and utilization of the entire cluster.
Phase 4: Commercialization & Go-to-Market (T+11 to T+14 Months)
- 3.13 Commercial Portal Development: Build and launch a secure, public-facing web portal for customers to purchase compute time, submit jobs, and manage their accounts.
- 3.14 Billing & Payment Integration: Integrate a secure billing system to handle transactions and automate payouts to the community cooperative and individual Hosts.
- 3.15 Initial Service Offering (ISO): Define and package the initial set of compute services, targeting “embarrassingly parallel” workloads like 3D rendering, scientific simulation, and AI inference.
Phase 5: Operations, Training & Handover (T+13 to T+15 Months)
- 3.16 Local Operator Training: Provide comprehensive training to the designated local communications entity (e.g., “TrifiWireless [Municipality Name]”) on the day-to-day operation and management of the cluster.
- 3.17 Documentation & Playbooks: Deliver a complete set of technical documentation, operational playbooks, and emergency procedures.
- 3.18 Project Handover: Formally hand over primary operational control to the local entity, with DeReticular moving into a long-term support and advisory role.
4.0 Key Deliverables
| Phase | Key Deliverable |
| 1 | Detailed Project Plan & Finalized Network Architecture Document. Signed agreements from 1,000 Hosts. |
| 2 | 1,000 physically installed and powered-on server nodes. A fully commissioned and tested Wi-Fi 7 mesh network. |
| 3 | A fully operational and centrally managed software orchestration platform. A live performance monitoring dashboard. |
| 4 | A public, transaction-ready commercial compute portal. Successful completion of the first paid compute job. |
| 5 | A trained local operations team. A complete set of technical and operational documentation. |
5.0 Project Timeline (High-Level)
- Months 1-3: Phase 1 – Planning & Design
- Months 4-9: Phase 2 – Physical Deployment
- Months 8-12: Phase 3 – Software Orchestration
- Months 11-14: Phase 4 – Commercialization
- Months 13-15: Phase 5 – Operations & Handover
6.0 Assumptions & Dependencies
- Client will secure all necessary municipal permits and rights-of-way for network hardware installation.
- Client will facilitate introductions and provide support for the community engagement and Host recruitment process.
- Host locations will have access to sufficient and stable electrical power.
- Global supply chains for NVIDIA H100 servers and networking components remain stable.
- The workload profile is primarily suited for distributed, non-tightly-coupled compute tasks.
7.0 Acceptance Criteria
This project will be considered complete and ready for final acceptance upon the successful achievement of the following criteria:
- All 1,000 NVIDIA H100 nodes are online, healthy, and manageable from the central orchestration platform.
- The Wi-Fi 7 mesh network meets the performance and stability metrics defined in the Architecture Document.
- The commercial portal is live and has successfully processed at least one paid compute job from an external customer.
- The local operations team has been trained and has successfully managed the cluster for a 30-day period with support from DeReticular.
8.0 Pricing and Payment Schedule
This section provides a framework for pricing. Actual costs are subject to a detailed quotation.
- Hardware Costs: [Cost of 1,000x H100 Servers + Networking Gear + Deployment Kits]
- Software & Licensing: [Cost for Orchestration, RIOS, and Management Software]
- Professional Services (Deployment & Integration): [Fixed Fee for aforestated Scope of Work]
- Ongoing Support & Advisory (Post-Handover): [Annual Retainer]
Payment Schedule:
- 20% upon SOW execution (to initiate procurement).
- 30% upon completion of Phase 2 (Physical Deployment).
- 30% upon completion of Phase 3 (Software Orchestration).
- 20% upon final project acceptance.
9.0 Authorization
The signatures below indicate the parties’ agreement to the terms outlined in this Statement of Work.
For [Municipality Name / Local Cooperative Entity]:
Name:
Title:
Date:
For DeReticular:
Name:
Title:
Date: